How can I see the percentage of complete work in the current iteration in TFS?
We need to display a chart that will display the specification of the completed work for several projects in some collection of projects, say the well-known DefualtCollection . So, if, for example, we have 3 projects in a collection, projects 1 , 2 and 3 , and project 1 has completed 30% of its tasks, 2 has completed 57%, and 3 has completed 20% of its tasks, I want the diagram to show that something like this: <sh>
Each project has its own path to the area. How can we achieve this?
+3
source to share
1 answer
You can use TFS storage based excel report. A reporting warehouse is a traditional data warehouse consisting of a relational database and an Analysis Services database.
See below for details: Managing a Data Warehouse and Analysis Services Cube
+1